Physical Plant Project Update, May 2007

Capital Projects:
 

“Tiger Village” Privately Developed Student Housing

  • Project is approximately 70% complete overall
  • Drywall hanging complete; drywall finishing 75% complete
  • Tubs and showers set in place
  • Lobby framing complete and rear columns masonry going up
  • HVAC rough-in complete except for lobby
  • Insulation complete
  • Roofing complete except for flashing, gutters and vent grates
  • Electrical/data feeds pulled through all floors
  • Site development 90% complete; paving complete except for service drive and final surface on Brooks Road

Clower Hall

  • Overall Project approximately 50% complete and on schedule for completion late July ‘07.
  • Floor repair 95% complete
  • New addition in place and dried-in
  • MEP rough-in complete
  • Water Main tie-in complete
  • Partition, office and snack bar framing complete
  • Roof pavers being installed

Stubbs Hall Renovation/Addition

  • Overall Project approximately 43% complete; scheduled completion October or November ‘07
  • Micro Lab, Anatomy Lab and Dr. Yeomans office relocated to Peterson Hall
  • Interior walls in Phase I renovation in place and drywall installation complete
  • MEP rough-in complete for renovated area and suspended ceiling going in
  • New addition walls in place; MEP rough-in 80% complete
  • Exterior brick on new addition complete; exterior panels will cover black area
  • Windows being framed for installation and roof nearing completion
  • Overall Project approximately 43% complete; scheduled completion October or November ‘07 

Major Repair and Renovation (MRR) Projects Regular:

  •  Engram Union Building, Replace Chiller; scheduled for December break
  • Richey Hall/Tanner Hall, Replace HVAC Units; contract let. ETC May ‘07
  • Campus Wide, Upgrade Storm Drainage System; Pending
  • Physical Plant Maintenance Shops Renovation; Pending
  • Library, Flooring Upgrade Phase I; on hold pending funds

MRR Projects Regulatory:

  • Campus Wide, Emergency Lighting Upgrades; Pending
  • Campus Wide, ADA Upgrades; contract let.  ETC Jun. ‘07
  • Campus Wide, Upgrade Fire Hydrant System; Pending 

Other Projects Ongoing:

  • Alumni House, ADA Renovations; Completed bathroom Dec.’06; contract let on front porch, wheelchair ramp and handicapped parking spaces.  ETC Jun. ‘07
  • Floyd Hall, Replace HVAC Chiller; currently monitoring oil analysis samples for further indication of bearing failure.  Will require emergency funding or reassignment of funds from other projects if replacement required.  Jun. ‘07
  • Grounds and Landscaping, Replace Sidewalks.  Complete unless DOC reverts to previous labor policy
  • Assist in developing Disaster Mitigation Plan (DMP) along with local Emergency Management officials and GEMA specialists

Miscellaneous:

  • Assist with preparations of grant applications and scope.  Apr ’07 and June ‘07
  • Assist in development of an Emergency Operations Template for the USG
  • Reviewing Golf Course development plan, target date Aug. ‘08

Notes:

Capital Projects are those that exceed one million dollars and usually refer to projects funded through GSFIC bond sales.  They are the only state funded source for new construction. 

MRR Projects are less than one million dollars in cost and are for repair, replacement or restoration only.  They cannot be used for new construction and are segregated into regular and regulatory categories by definition.  They can be funded by bond sales or direct allotment from the state legislature. 

Once a project in this report is shown as completed it will be removed from following updates.